MATERIAL HANDLING
The time has come to start installing the Dock Level Units at City Center. This is our Material Handling Department doing the install. Docks in one part of the large complex are done and ready. We now can install 7 Dock Level Units. The Dock Level Units have been at our warehouse for about a year weighting for this time to come. When done we will have installed 35 total units.
ENTERTAINMENT INSTALL
Monday starts our crews working with Stage Tech on the winch install in the ballrooms and the showroom.
No comments:
Post a Comment